By Obas Esiedesa, Abuja
The Niger Delta Power Holding Company Limited (NDPHC) has commenced a major electricity infrastructure project aimed at ending a 15-year blackout in Rigasa community, Igabi Local Government Area of Kaduna State.
The project, facilitated by the Bola Ahmed Tinubu Ideological Group (BAT-IG), comprises a two-kilometre 11kV line, a 1.5-kilometre 33kV line and a 7.5MVA, 33/11kV injection substation designed to strengthen electricity distribution and improve power supply to residents and businesses.
A statement by General Manager, Corporate Communication and External Relations, Nazo AGIM on Saturday explained that the project reached a major milestone on Friday with...